Nuclear Plants Not Y2K Ready
By The Associated Press
List of Nuclear Plants Not Y2K Ready
WASHINGTON (AP) - Commercial nuclear power plants that have actions
remaining to be completed to be fully Y2K ready and estimated dates of
completion, according to the U.S. Nuclear Regulatory Commission:
Beaver Valley, Units 1 and 2; Shippingport, Pa., 9/30/99.
Browns Ferry, Units 2 and 3; Athens, Ala., 10/31/99.
Brunswick, Unit 1; Southport, N.C., 11/30/99.
Clinton; Clinton, Ill., 9/22/99.
Comanche Peak, Unit 1; Glen Rose, Texas, 11/30/99.
Comanche Peak, Unit 2; Glen Rose, Texas, 10/30/99.
D.C. Cook, Units 1 and 2; Bridgman, Mich., 12/15/99.
Davis-Besse; Port Clinton, Ohio, 8/1/99.
Diablo Canyon, Units 1 and 2; San Luis Obispo, Calif., 10/31/99.
Farley, Unit 2; Columbia, Ala., 12/16/99.
Hope Creek; Hancocks Bridge, N.J., 10/29/99.
Limerick, Unit 2; Limerick, Pa., 9/30/99.
Monticello; Monticello, Minn., 9/1/99.
North Anna, Unit 2; Mineral, Va., 10/29/99.
Oyster Creek; Toms River, N.J., 9/30/99.
Peach Bottom, Unit 2; Delta, Pa., 9/30/99.
Peach Bottom, Unit 3; Delta, Pa., 10/31/99.
Perry; Perry, Ohio, 8/1/99.
Salem, Unit 1; Wilmington, Del., 11/6/99.
Salem, Unit 2; Hancocks, N.J., 10/29/99.
Sequoyah, Units 1 and 2; Soddy-Daisy, Tenn., 10/31/99.
South Texas, Units 1 and 2; Bay City, Texas, 10/31/99.
St. Lucie, Units 1 and 2; Fort Pierce, Fla., 7/15/99.
Three Mile Island, Unit 1; Middletown, Pa., 10/21/99.
Turkey Point, Units 3 and 4; Florida City, Fla., 7/15/99.
Vermont Yankee; Vernon, Vt., 10/31/99.
Watts Bar; Spring City, Tenn., 10/31/99.
Associated Press - See whole story here